Before Delivery
Complete drawings, foundation, access, grounding and cable interfaces.
Use this guide to coordinate delivery, receiving inspection, positioning, civil interfaces, grounding, electrical connections, commissioning and handover.
The sequence below is the organizing logic for this page and for the work on site.
Complete drawings, foundation, access, grounding and cable interfaces.
Inspect packaging, equipment condition, accessories and nameplate.
Use designated lifting points, level the unit and secure it correctly.
Complete drainage, conduits, working access and grounding.
Connect grounding, LV, HV, controls and protection in sequence.
Complete inspections, electrical tests and functional checks.
Energize progressively and transfer the operating record set.
Use the approved outline drawing to coordinate the foundation, cable entries, grounding, drainage, operating access and lifting route.
Confirm final footprint, equipment orientation, door opening and accessory positions.
Provide a level, load-bearing foundation sized for the actual transformer.
Coordinate trench, conduit location, sealing and cable bending space.
Provide accessible connection points based on the site grounding design.
Prevent standing water and provide oil containment where applicable.
Keep routes clear for transport, lifting, operation and future replacement.
Inspect the shipment before unloading, use the designated handling points and confirm the unit is level, secure and undamaged after positioning.
Transformer mass, center of gravity, lifting points and accessory arrangement vary by model. Do not infer a lifting method from product appearance.
Select the installed transformer type to see the site issues that require the most attention.
Prepare a level concrete pad, underground cable entries, permanent grounding, drainage, lockable access and unobstructed operating space.
Plan 10 ft at the front operating side, 8 ft on the left, and 3 ft at the rear and right; allow 5 ft on the right when metering is inside. Keep combustible structures 10 ft away and maintain 3 ft from non-combustible structures where permitted. These distances support door operation, maintenance access and fire separation; use the approved layout and local utility rules for the final arrangement.
Grounding comes first. Before energization, the approved drawing, transformer nameplate and site system must agree.
Connect the tank and required neutral points to the site grounding system.
Seal conduits and support cables without excessive force on terminals.
Complete low-voltage connections to the approved terminal arrangement.
Complete primary connections after grounding and LV work are checked.
Confirm neutral, phase relation, vector group and system grounding.
Check tap position, controls, alarms and protection wiring while de-energized.
Physical, mechanical, electrical, protection and document readiness must all be confirmed by the responsible site team.
| Commissioning check | Typical activity | Purpose |
|---|---|---|
| Insulation and winding condition | Insulation resistance and winding resistance | Confirm insulation condition and conductor continuity |
| Ratio and connections | Turns ratio, polarity, phase relation and vector group | Confirm winding relationship and site connections |
| Protection and alarms | Gas, temperature, pressure, liquid-level and trip/alarm circuits | Confirm functional response and signal routing |
| Tap equipment | Position, indication and permitted operation | Confirm voltage setting and control function |
| Insulating liquid | Liquid level, breakdown voltage and analysis where required | Confirm the condition of the insulating medium |
Use the product manual for the pressure and liquid-level procedure. The manual specifies no more than 7 psig, a hold of at least 4 hours, and its liquid-level reference at 25°C.
The factory-filled mineral oil specification includes ASTM D-877 dielectric strength of at least 30 kV and PCB content below 2 ppm. Apply the acceptance procedure stated for the supplied unit.
Proceed only after authorization, then observe the transformer at no load before applying load in controlled stages.
Confirm responsibilities, switching plan and permission to energize.
Energize under the approved operating procedure without connected load.
Check voltage, current, sound, leakage, pressure, temperature and alarms.
Increase load progressively while monitoring voltage and thermal behavior.
Record load, voltage, current, balance, temperature and protection status.
Close actions and transfer the equipment and records to the operating team.
Final layout, terminal arrangement, wiring and accessory drawings.
Approved ratings, impedance, vector group, taps and cooling.
Applicable factory, FAT, site and commissioning reports.
Product operating, inspection, maintenance and safety instructions.
Parts referenced to nameplate kVA, voltage and serial number.
Closed punch list, energization approval and signed handover.